A pays Rs. 10,000 to B for manufacturing a machine. When it is partly manufactured, the contract is discharged by frustration. What is the remedy available to parties?
A. A can recover Rs. 10,000 from B
B. A need not pay any further amount to B
C. B can retain Rs. 10,000
D. B is entitled only to expenses incurred before the time of discharge
Answer: Option D